News and promotions
15.05.2017
Live And Do Not Pay!

The Sky Skolkovo complex of business-class apartments and Absolut Bank launch the ““Live And Do Not Pay” program in the Sky Skolkovo apartment complex . The program will allow customers to get a mortgage for buying a house and not to pay mandatory monthly repayment on a given loan...

05.05.2017
Credit period – from 3 up to 30 years.

Dear Clients! The Sky Skolkovo team congratulates you on the coming Victory Day! On May 6-8, the sales office is open as usual during this time. May 9: from 10.00 till 20.00

04.05.2017
Construction news from the Sky Skolkovo site

1. The lining of the basement is close to its completion, it is a suspended ventilated façade made of a composite panel. 2. Active work is underway to finish the first floor. The walls and the floor are ready to be tiled with ceramic tiles in the common areas. The...

03.05.2017
A special entry road to the Moscow Ring Road for the residents has been opened.

Sky Skolkovo residents have a separate exit/entrance, which will allow them to reach Moscow in 2 minutes (400 metre road). Let us recall that earlier the exit road to the Moscow MKAD Ring Road and further towards the centre was in the vicinity of Trekhgorka; it took the driver about 20...

30.03.2017
Minimum prices for apartments

Dear clients, Hurry up to buy apartments at a special price! Hurry up to buy apartments at a special price! Please note these terms are valid for a limited period of time provided a 100% payment is made and mortgage is taken out. April 24 will see the opening of the club exit...

29.03.2017
The residents have their own entry road to the Moscow Ring Road

Sky Skolkovo residents have a separate exit/entrance, which will allow them to reach Moscow MKAD Ring Road in 2 minutes (400 metre road). Let us recall that earlier the exit road to the Moscow MKAD Ring Road and further towards the centre was in the vicinity of Trekhgorka; it took the...

09.03.2017
Construction news from the Sky Skolkovo site

Finishing works on staircases are coming to an end. Detailed information on the progress of the construction can be obtained at the sales office or by phone 8 495 1070077

07.03.2017
Mortgage credit from the DeltaCredit Bank is 8.5%

Dear clients, The interest rate on the mortgage from the DeltaCredit Bank is subsidized by 8.75% for the entire crediting period. Credit period – up to 25 years The interest rate for payroll customers in the Bank is 8.5 percent per annum. Details on the terms of the loan can be obtained at...

06.03.2017
THE SALES OFFICE WORKING HOURS ON MARCH 8

The Sky Skolkovo team most heartily congratulates you on the coming Victory Day! Let there always be laughter in your family and let the warm spring sunshine in! Please note that on holidays the sales office at the facility operates normally from 09:00 to 00:21.

28.02.2017
Mortgage credit from SberBank is 10.9%

Dear clients, Sky Skolkovo is accredited by Sberbank. The minimum mortgage interest rate is 10.9%. The first payments under this program are only 15% of the cost of the apartment. The credit period will be up to 30 years. The rate is valid provided that the life and health of the borrower are...

21.02.2017
Sales office working hours on February 23-26:

Dear Clients, The Sky Skolkovo team most heartily congratulates you on the Defender of the Fatherland Day! Please note that on holidays the sales office at the facility operates on February 23-26 from 10:00 to 00:20. Starting from February 27 we shall work for you as usual from 09:00 to 00:21.

18.01.2017
The whole world is in Sky Skolkovo

The individual decoration of the public accommodations on each floor of the Sky Skolkovo apartment complex is one of its unique features. The walls in the halls at different floors of the building will depict panoramas of the world’s largest metropolitan areas, which are their architectural landmarks. And the floors...

13.01.2017
Mortgage loans from DeltaCredit Bank

Dear clients, Sky Skolkovo is accredited by DeltaCredit Bank. The minimum mortgage interest rate will be from 10,75% *, and the first installment under this program is 50% of the cost of the apartment. Credit period – up to 25 years Details on the terms of the loan can be obtained at the...

11.01.2017
Construction news from the Sky Skolkovo site

Our clients are already enjoying comfortable and warm atmosphere our apartment complex offers! The heating has been put on in most sections. Sky Skolkovo has installed rooftop gas boiler houses, which have a number of advantages over their counterparts. Such systems allow for fine temperature setting in each apartment depending on...

26.12.2016
Sales office working hours on New Year holidays

The Sky Skolkovo team congratulates you on the upcoming holidays and wishes you all the best in the New Year! May you be blessed enough to spend this new year with your parents, friends, loved ones. On holidays the sales office is open on: December 31 – from 09:00 to 15:00 January 1,...

21.12.2016
Construction news from the Sky Skolkovo site

The installation of entrance doors to the apartments on the third floor is underway. The thickness of the door is 10 cm; a 10 mm double-sided MDF (Medium Density Fiberboard) panel is covered with the ““Antique Oak” wear-resistant high-tech colour film. Details on the construction progress can be obtained at the...

20.12.2016
Railway communication between the Belorusian railway station and Odintsovo will be established at the end of 2017.

The railway line from the Belorusian railway station to Odintsovo is planned to be commissioned by the end of next year. There will be four stops on this line: ““Belorussky Railway Station”“, ““City”“, ““Slavyansky Boulevard”“ and ““Odintsovo”. One of the stops will be a transport hub on the territory...

08.12.2016
Construction news from the SKY SKOLKOVO site

The Doppler Line 2000 elevators are installed in all sections. Details on the construction progress can be obtained at the sales office or by phone +7 (495) 151 17 57.

02.12.2016
The “Decoration As A Gift” promotion

Dear Clients, The New Year is coming and it is time for presents! If you purchase an apartment before December 31, 2016, you will receive a decoration as a gift *. These conditions and terms apply to a limited number of apartments, provided full payment is made and mortgage is taken...

02.12.2016
Credit period – from 3 up to 30 years.

Dear clients, For your convenience, the sales office on site is open daily from 09:00 to 00:21 without holidays. We are waiting for you!

01.12.2016
Construction news from the Sky Skolkovo site

The rate of building in the apartment complex is not slowing down! Valves are welded to the fire fighting pipes. After common areas fire alarm wiring is being installed in the apartments. At present, rising pipes are being connected to the heating radiators. Hot and cold water supply...

28.11.2016
Construction news from the Sky Skolkovo site

At present, active work is underway with the apartments being pre-finishing. Doppler Line 2000 lift doors are installed in all sections. Works on the installation of smoke and heat smoke exhaust ventilation systems are coming to an end. Details on the construction progress can be obtained at the sales office or by...

25.11.2016
MORTGAGE LOANS FROM ABSOLUT BANK

Dear clients, Sky Skolkovo is accredited by Absolut Bank. An interest rate for the whole period of mortgage will be from 12%, down payment is 30% of the cost of the apartment. Credit period – up to 25 years Details on the terms of the loan can be obtained at the sales office...

03.11.2016
Working hours on public holidays

Dear clients, The SKY Skolkovo team congratulates you on the upcoming National Unity Day! On November 4-6, our sales office operates from 10:00 to 00:20 (days off schedule). We are waiting for you!

27.10.2016
A relief road of Kutuzovsky Prospect in the south will be extended to Moscow MKAD Ring Road

The southern relief road of Kutuzovsky Prospekt is planned to be extended to the Moscow Ring Road and get connected with General Dorokhov Street. The first stage of construction is the extension of Mosfilmovskaya street from Amin’evskoe highway to Minskaya street. “As to the Minskaya street, there will be a metro...

24.10.2016
Mortgage loans from Vozrozhdeniye Bank

Dear clients, Sky Skolkovo is accredited by Vozrozhdeniye Bank. The interest rate on the mortgage will be from 12.8%, the down payment is 20% of the cost of the apartment. Credit period – 30 years Details on the terms of the loan can be obtained at the sales office or by phone +7...

12.10.2016
SMP Bank has accredited Sky Skolkovo

Dear clients, Now you can purchase apartments using a mortgage from SMP Bank. The interest rate on the mortgage will be from 12.5% *, the initial installment – 30% of the cost of the apartment. There is no limit on the maximum amount of the loan. Details on the terms of the loan...

28.09.2016
Design drawings of a medical cluster in Skolkovo are ready

A design of the medical-diagnostic building was completed at the International Medical Cluster in Skolkovo. The total area of the facility is 13,000 sq. m (4 floors). It will be connected with the therapeutic building through the Winter Garden. The diagnostic building will house consulting rooms, as well as a training centre...

19.09.2016
Construction of a sewage treatment plant in Skolkovo

A range of treatment facilities will be launched at Skolkovskoye Highway by October. The construction is coming to an end. A representative of the Moscow Department of Construction said that the new complex will improve the environmental situation in the west of Moscow and improve the quality of water in the Setun...

12.09.2016
Mortgage with "VTB24”

Dear clients, We are glad to inform you that Sky Skolkovo is now accredited by VTB24. The interest rate on the mortgage will be from 13.6%, the down payment is 20% of the cost of the apartment. Credit period – 30 years A mortgage is possible “with two documents”. Details on the...

24.08.2016
By 2019, Moscow will build a northern relief road of Kutuzovsky Prospekt

According to Deputy Mayor of Moscow Marat Khusnullin, the construction sites have already been cleared for use. It is expected that the Northern relief road will be built in 2019. It will be a continuation of the high-speed road bypassing Odintsovo and running to the Moscow International Business Center along...

19.08.2016
Installation of elevators

Today, installation of elevators has begun in the first section of Sky Skolkovo. It is planned to come to an end with the installation of lift equipment until the end of the month. Six modern Doppler passenger lifts of LINE 2000 model will be installed in the building. The equipment of this...

19.08.2016
A group of landscape parks will be set in Skolkovo

Landscaped parks will be laid out on the premises of the Skolkovo innovation center. Each park will have its own thematic scope. In addition, they are connected with a walking route of about five kilometers. The parks will have bicycle and segway rental offices, as well as free charging points for...

16.08.2016
Construction of the medical cluster in Skolkovo

The construction of the first international medical cluster in Russia began in Skolkovo. A time capsule was laid in the foundation by Moscow Mayor Sergei Sobyanin. The cluster will be built at the center of innovation and modern technologies ‘Skolkovo’, the total building area is 57.6 hectares. In the next 10...

15.08.2016
Construction of a road in Novaya Trekhgorka

Representatives of the Odintsovo District reported that by the end of 2016 a road will be built to connect the neighborhood of Novaya Trekhgorka with a toll motorway (Northern Bypass of Odintsovo). Now the preparatory work is underway. The opening of the road will help optimize traffic flows, save time...

10.08.2016
Sky Skolkovo infrastructure

Sky Skolkovo is a modern complex of apartments with concierge service for the convenience of residents. The first floors are planned to accommodate small shops where you can buy essential goods. But the Vegas Kuntsevo shopping and recreation center which is planned to be located just 2 km from the site is...

10.08.2016
Sky Skolkovo Construction News

The construction facility is being constructed at a fast pace. The construction fence around the house is removed and improvement of the adjacent territories began. Heating radiators are installed in the first section. A high-voltage cable is laid for electricity supply. Doppler lifts (Greece) are ready and will be installed before the...

11.07.2016
Sky Skolkovo Apartments - soon available!

“StroyProfil” group of companies is proud to announce the start of sales occurring in the near future in Sky Skolkovo apartments on Ovrazhnaya street, 47. The reservation service is open now. For more information, please contact the sales office or call +7 (495) 104-29-99. +7 (495) 104-29-99